





Phase 1 December 2021 – July 2022
Contractor: Northern Construction
• Demolition
• General Site Requirements:
o Siltation Control
o Fill
o Rough Grading
o Fine Grading
o Asphalt Walkway
▪ Base 250 mm
▪ Sub-base 300 mm
o Crusherdust trail
▪ Base 250 mm
o Bleacher pads
o Bench pads
• Field Construction:
o Outfield seeding
▪ Topsoil 250 mm
▪ Drainage 100 mm sand
o Pitcher’s mound electrical outlet
o Foul line
o Crusher dust warning track
▪ Crusherdust 100 mm
▪ Gravel base 250 mm
o Plates
o Bases
o Outfield drainage tile
o Infield drainage tile
o Electrical conduit
o Artificial Turf infield – Purchase
o Artificial turf infield – Installation
• Fencing
o 2.4 m fence
o Backstop
o Foul poles
o Safe foam on fence
o Gates
o Dugout
• Landscaping/Outside Field
o Hydraulic seeding
▪ Topsoil 250 mm
o Trees
• Civil Works
-----------------------------------------------------------
Phase 2 July 2022 – Spring 2023
Contractor: Joneljim Concrete Construction
• Ballfield
o Portable Pitcher’s Mound
▪ Electrical
o Field Lighting
▪ Electrical
o Score Clock
▪ Electrical
• Site Furnishings
o Benches
o Path Lighting
▪ Electrical
o Lighting Foundation & Conduit
o Folding Fence Chairs
o Bike Rack
o Bleacher Roof
o Flag Poles
o Trees
o Trash Receptacle
o Bocce Court
o Donor Wall/Entry Sign
• Building
o Full Installation
o Service Connections
o Mural
• Splash Pad
o Sitework
o Fixtures
o Installation
o Concrete Pad
o Mechanical & Electrical
o Asphalt Walkway
▪ Base 250 mm
▪ Subbase 300 mm
o Landscaping
o Miscellaneous